[Completion on the Air Separation Unit (ASU) design] The Basic and Detailed Engineering for Industrial Gas Storage Facility in Yeongilman, Pohang
- okenco2017
- Aug 26
- 2 min read
E&CO LTD. has successfully completed the basic and detailed engineering services for an industrial gas storage facility located in the Yeongilman A Industrial Complex in Pohang, under operating with Company P. The goal of this project was to establish a stable supply infrastructure for industrial liquefied gases—such as those used in the secondary battery specialized complex—while also enabling external sales of these gases. To achieve this, a new facility for the production, storage, and supply of industrial gases was required.
E&CO LTD. was responsible for three major categories of engineering: Site installation and layout for gas supply facilities, Mechanical (including piping) and electrical/instrumentation/control (EIC) systems, Utility supply infrastructure. The scope included the design of storage vessels for liquefied hydrogen (LH₂), nitrogen (LN₂), and argon (LAr), along with associated vaporizers and boilers. Especially, It is also performed piping and instrumentation design, and electrical/control system engineering. All engineering deliverables were prepared in full compliance with KGS (Korea Gas Safety) codes, as well as international standards including API 620 and API 650. E&CO LTD. submitted all necessary documents required for technical review by KGS and for the final facility inspection certificate.
Completed this project, E&CO LTD. will demonstrate the engineering expertise in the growing secondary battery sector by completing the basic and detailed design of an Air Separation Unit (ASU) for supplying high-purity oxygen and nitrogen used in precursor production, cathode material processing, and nickel refining.
주식회사 이앤코가 P사가 운영하는 포항시 A산업단지 내 산업가스 저장설비 기본, 상세설계 용역을 완료했다. 이번 사업의 궁극적인 목표는 이차전지 특화단지 내 산업가스 액제품을 외부로 판매함과 동시에 가스공급을 안정화 하는 것이고, 이를 위해서 먼저 산업가스 생산·저장·공급 설비를 신설하여 인프라 구축이 필요했다.
이앤코는 크게 세 가지 설계 (공급설비를 현장에 설치위한 설계, 기계(배관공사 포함) 및 전기 전기·계장공사를 위한 설계, Utility 공급 공사를 위한 설계)를 담당했으며, 구체적으로 가스 저장설비에 설치되는 액화 수소(LH2), 질소(LN₂), 아르곤(LAr) 저장 용기와 기화기 및 보일러를 포함한 장비리스트, Piping, Instrument, EIC(Electrical, Instrumentation & Control)의 설계를 수행했다. 또한 모든 설계도서와 문서는 KGS 코드와 API 620 & API 650을 준수하여 작성됐으며, KGS 기술검토 접수 후 완성검사 필증 수령에 필요한 도서까지 제출했다.
양극재, 전구체 생산공정 및 니켈 정제공정에 사용될 고순도 산소와 질소를 공급하는 데에 필요한 공기분리장치 (ASU: Air Separation Unit) 설비 기본, 상세설계 실적을 통해 이앤코는 차세대 주력산업으로 부상하고 있는 이차전지 산업에서도 플랜트 엔지니어링 경쟁력을 선보일 예정이다.


<3D modeling of the Air Separation Unit (ASU) facility>